New UX: Add ETC by tasks assignments

Idea created by Zaina_Din on Apr 12, 2019
    New
    Score1
    • Zaina_Din

    Hello, in the current release 15.6, it not possible to edit in the new experience , ETC by ressources assigned to task. And BNPP BDDF wish to have it to complete the workflow of project management. Here you are the workflow of project management:

    ==> Create a project and fill properties: OK in the new UX

    ==> Allocate ressource (staff the project): OK in the new UX

    ==> Create tasks and assign resources to these tasks: OK in the new UX

    ==> Add global ETC to task level: OK in the new UX

    ==> Divide by resource ETC of tasks: KO in the new UX

     

    eg: Task conception: 30 hours of ETC

                        Resource A: 15 hours of ETC

                         Resource B: 15 hours of ETC

                         

    This is not possible actually.

     

    Thanks you.

     

    Bests regards.

     

    Zaïna DIN